TRAFFIC IMPACT: US Route 2 at the temporary drawbridge is open to two lanes of traffic. The contractor will be working from 7:00 AM to 5:30 PM, Monday through Thursday. They will be working from 7:00 AM Friday through 12:00 PM on Saturday.
The temporary bridge has a speed limit of 25 mph. There are tight curves approaching the temporary bridge, and trucks are advised to reduce speed to 15 mph. Bicycles should use caution while crossing the bridge.
The work zone speed limit is enforced, and individuals have been ticketed for excessive speeding. Obeying the speed limit is extremely important for everyone’s safety.
NOTICE TO MARINERS:The drawbridge has ended its daily operating schedule, and will resume May 15, 2021.
All mariners must pass with extreme caution and NO WAKE.
To request an opening or to communicate with the bridge tender, please use Channel 13 or 802-372-4360.
CONSTRUCTION ACTIVITIES:
The contractor has continued excavating the cofferdam with the crane and clam bucket through this week on the east side of the existing bridge. They will be pouring concrete Friday (10/23) evening for the new pier subfooting. There will be continuous construction activity both during the day and night on Friday, and through mid-morning on Saturday.
On the west side of the existing bridge, the contractor has completed removal of the existing pier near the shore. The demolition contractor is demobilizing from this side of the bridge.
As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.